hospitality news Autumn 2007

Have you heard the one about the construction project finishing on time and on budget?

With the press constantly reporting on projects being completed late and over budget, the concept of 'on time and on budget' has become a running joke. However, this is a very serious issue for hotels undertaking construction works, particularly where the hotel stays open during the works and future bookings rely on completion by a particular date. Every hotel owner knows that delays can be very costly, not only in relation to the costs of the construction works themselves but also in terms of lost business.

It is almost impossible to guarantee that a project will be delivered on time and on budget, but it does happen, and there are many things that you can do to increase your chances of achieving it.

On time

It is essential to have a building contract setting out exactly what has been agreed between you and your contractor. It should include a clear specification of what is to be done, a price and a completion date. Most building contracts provide for liquidated and ascertained damages to be paid by the contractor in the event that the project is late due to contractor's fault. Without such damages the contractor will have less incentive to prioritise your job over anyone else's. The damages are intended to be a genuine pre-estimate of the losses you are likely to suffer if the project is late, for example if you are unable to fulfil bookings or have to turn guests away. However, if your losses are likely to be high when compared with the cost of the works, the contractor may be unable to accept the risk of the proposed level of damages without increasing his price to an unacceptable level. So what else can you do?

Once you have received the contractor's price, consider inserting further incentives into the contract terms, for example:

On budget

The two main areas where costs can escalate relate to changes of design and provisional sums.

Many cost overruns (and indeed delays) are due to changes in design being requested by the employer once the contractor has already entered into the building contract. Whether you require the contractor to take on design responsibility or not, you really need to aim to have finalised all the information that you and, if appropriate, your designers are providing to the contractor before they start to price the job. If you do not and what you want or your information subsequently changes, the contractor is likely to be entitled to both additional time for completion and money.

Provisional sums are estimated prices for items of work that the contractor cannot accurately price, usually because he does not have enough design information from his employer. If when the contractor comes to do that work the price has gone up and exceeds the provisional sum, the contractor will be entitled to additional payment. Prices relating to statutory services (gas, water, electricity) are almost always provisional, as it is difficult for the contractor to estimate how much will be charged by the relevant statutory authority; however, often other items of work are also priced as provisional sums. You should aim to reduce these to only the most essential. Provided you are able to give the contractor sufficient information, this should be achievable.

Checklist:

Choosing your contractor

Getting the contract right

During construction

Sarah Elliott
Construction